Schedule prior to Pre-deployment Integration with LDB support Systems
Major Program Milestones
- Project Initiation Conference Jan 28, 1999
- Pre-Campaign Conference Feb. 5-6, 1999
- Review of Thermal and Mechanical Certification TBD
Hardware
- Complete LOS data COM port
- Fabricate 2 lower solar array frames and assemble solar arrays and functional test
- Fabricate tow balloon release mechanisms
- Thermal Vacuum test Feb. 14-28, 1999
- Mass properties Verify Mass and C.G. of Spinner
- Strength test of light shield/spinner to tow balloon suspension cable attachment